PROJECT SCHEDULE: 2007

 
Project Description
Corridor Alternatives
Environmental Review
Funding
Public Outreach
Project Schedule
Project Library
Who to Contact
   
   
   
   
   
   
   
   
   


 

   
Public Outreach Month Technical Process
  January Drafts submitted to Caltrans:
  • Air Quality Technical Memorandum
  • Traffic Noise Analysis Technical Memorandum
  • Public Participation Methodology Report
February 2007 Newsletter February Caltrans accepted all draft technical reports

1st Admin. Draft Tier 1 distributed for Caltrans review

  March Project Development Team Meeting #17

Caltrans submitted 1st Admin. Draft Tier 1 comments

Placer Co. Board of Supervisor’s briefings April Caltrans completed 2nd Admin. Draft comments
  May MEPLAN Technical Report

FHWA Briefing: Draft Tier 1 EIS/EIR & technical reports

Sutter Co. Briefing: Draft Tier 1 EIS/EIR & technical Reports

Admin. Draft: Interim Report: Summary of Modified NEPA/404 Consultation through Concurrence Point #3

FHWA & Sutter Co. completed draft comments

Draft Engineering Summary Report completed

Notice of Availability

Press Release

June Modified NEPA/404 Meeting #17

Notice of Completion (State Clearinghouse)

Draft Tier 1 EIS/EIR distributed for public comment & review

July 2007 Newsletter

July Public comment period begins

SPRTA Board Public Hearings to get comments on Draft Tier 1 EIS/EIR:
Yuba City - August 6
Roseville - August 8

August  
  September Public Comment Period Closes

Project Update: Sun City Roseville, Community Relations Committee

October  
  November Modified NEPA/404 Meeting #18
  December  
 


Project Description | Corridor Alternatives | Environmental Review | Funding | Public Outreach | Project Schedule | Project Library | Who to Contact

Placer County Transportation Planning Agency
299 Nevada Street  ● Auburn, CA 95603
(530) 823-4030 ● (530) 823-4036 - fax
email PCTPA